Nechako Centre in Kitimat

Nechako Centre Demolition

From November through to January, the project to demolish 110-139 & 143 Nechako Centre will take place.

Key Dates

[This original schedule is being revised due to unexpected challenges to the contractor's plan. We will revise once we are aware of the new dates.]

Tuesday 12 November 2024

Site mobilization

Site mobilization begins and fencing is installed around the worksite.

Thursday 14 November 2024

Abatement phase (Estimated start)

The Hazardous Building Materials Abatement phase begins, as building waste will be removed and hauled from the site.

Monday 16 December 2024

Demolition phase (Estimated start)

The demolition phase begins, as the pieces of the structure start getting removed.

How this will affect the parking area

During this project, more vehicle and pedestrian traffic is anticipated on Plover, Oriole, and Pintail streets on school days between 8:30 a.m. and 8:45 a.m., and 2:30 p.m. and 3:10 p.m.

See the below images for more details on how the parking lot will be arranged during this work.

What happens after demolition?

Work is happening to bridge the existing Nechako Centre Concept Plan (see other tab) to a realized, developed site.

In October, the District of Kitimat planning department was directed by Council to issue an RFP to find a consultant to create a development plan for this property.

While the concept plan took community input to determine what type of services or amenities residents want to see at this property, a development plan means taking a closer look at what steps need to be taken to realize those concepts. This can include things such as looking at utilities, services, the technical considerations of the ground, and how development may impact surrounding land users.


Nechako Centre Concept Plan

Nechako Centre is located within the Nechako neighbourhood and is accessible from Kingfisher Avenue. It used to be a popular and well used commercial area but has seen a noticeable decline in the commercial uses offered since the late 70s and early 80s. In 2021, the District of Kitimat hired a consultant to complete a market assessment and concept plan for Nechako Centre. The assessment and plan were completed in the end of 2022 and was presented to Council on December 5, 2022.

With the concept plan completed, the District is looking towards the creation of a development plan that will take the concept plans to the next stage.

What are the concepts

The concept plan is thorough, but here are some of the visions for Nechako Centre as outlined in the plan. Refer to the full concept plan for more details and other visions.