Some might find the subject a bit dry, but we’re excited to be embarking on a multi-year project to upgrade the community’s water system.

In order to meet modern regulatory requirements - and in doing so prevent future water quality advisories - we will be upgrading our water system in a number of ways;

  • Water conditioning.
  • Direct sand filtration.
  • UV disinfection.

The pilot plant commissioned in 2022 proved the design concept and provided valuable data on how our water responds with treatment products. Public Works continues to operate the pilot plant to gain experience needed for operators to obtain higher certification.

The detailed design for this plant was recently completed. Construction of the new treatment system will commence this year.

News

Updates to Kitimat's Water Treatment Upgrade Project

Timeline of milestones

Timeline

  • Timeline item 1 - complete

    Pilot plant study

    Completed December 2022

    Study conducted to prove design concept. Public Works continues to operate the pilot plant for our operators to gain experience required to obtain a higher level of certification

  • Timeline item 2 - complete

    Preliminary Design

    Completed March 2023

    Development of the terms of reference for process equipment, site selection, and preliminary building layout.

  • Timeline item 3 - complete

    Detailed Design

    Completed December 2024

    Preparation of design drawings and specifications to tender the construction and commissioning scope of work.

  • Timeline item 4 - complete

    Funding

    This project is being funded through District budget allocation, temporary borrowing through the Municipal Finance Authority, Northwest BC Resource Benefits Alliance funding, and Canada-British Columbia Investing in Canada Infrastructure Program – Green Infrastructure Grant.

  • Timeline item 5 - complete

    Construction permit received from Northern Health

    Completed January 29, 2025

    A required construction permit from Northern Health for the construction of the water treatment plant was received here.

  • Timeline item 6 - active

    Construction of water treatment plant

    Through 2025 and parts of 2026

  • Timeline item 7 - incomplete

    Commissioning of Water Treatment Plant

    In 2026

    Once completed, the new water plant will provide clean water to the community, and nearly all water advisories should be eliminated from this point onwards.

This project is funded in part by the Government of Canada.